Place: London
Architect: Duggan Morris Architects
Start on site date: September 2009
Contract duration: 35 weeks
Gross internal floor area in m2: 140sqm gross area
Form of contract: JCT Intermediate Form with subcontractors design portion
Total cost: £320,000
Cost per m2: £2285.00
Client: Private
Structural engineer: Lyons O’Neill
Environmental Design Consultant: Brooks Devlin
Party wall Surveyor: BCS Consulting
Main contractor: ME Construction Ltd
Annual CO2 emissions: 2825KgCO2/yr (Combined total for space heating, DHW = 2375KgCO2/yr. Pumps, fans and lighting = 450KgCO2/yr)